PTSC M&C Sends Four Baltica 2 Substations from Vietnam to Europe

PTSC M&C has completed a 43-day load-out campaign for four Baltica 2 offshore substations and four support frames, with the approximately 16,000 t shipment moving from Vietnam to Europe.
Photo credit: PTSC M&C

SHARE ARTICLE

PTSC M&C has completed a 43-day load-out campaign for four offshore substation topsides and four modular support frames for the 1.5 GW Baltica 2 offshore wind farm, moving the structures from Vietnam toward Europe.

The eight structures have a combined weight of approximately 16,000 t. They were fabricated and loaded out at PTSC M&C’s facilities in Vung Tau.

A load-out and handover ceremony was held on 12 September 2026. At that time, two of the offshore substations were already being transported to Europe, while the other two had been loaded onto transport barges at the PTSC port ahead of sail-away.

The shipment is the first delivery of offshore substations manufactured by PTSC M&C in Vietnam for the European market.

The structures are destined for Baltica 2, an offshore wind farm being developed by PGE and Ørsted in the Polish Baltic Sea. The project has a planned capacity of approximately 1.5 GW and will use 107 wind turbines and four offshore substations.

Each of the four offshore substations is rated at 375 MW. The substations were awarded to a consortium of Semco Maritime and PTSC M&C under an engineering, procurement and construction contract announced on 13 June 2023. The contract covers design, engineering, procurement, construction and commissioning.

The four substations were manufactured at PTSC M&C’s Vung Tau yard. Semco Maritime and PTSC M&C are supported by ISC Consulting Engineers and Hyundai Electric as primary subcontractors for the package.

Offshore construction of Baltica 2 has also progressed in Poland. PGE and Ørsted completed the installation of all 111 monopile foundations on 21 August 2026. Of these, 107 support the wind turbines and four are for the offshore substations.

The developers said in August that preparations were underway for installation of the offshore substations and export cables later in 2026.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Steelwind Nordenham is loading Hornsea 3 monopiles weighing up to 2,050 tonnes using two 900-tonne quay cranes and a 1,600-tonne crawler crane in Germany.
A dedicated pontoon handles power, spare and fibre-optic cables together for TenneT’s two grid links, with vertical water-jet burial and installation scheduled to continue into spring 2027.
Masdar's debut blue bond attracted US$1.5 billion in investor orders. The five-year issue carries an AA- rating, with proceeds intended for eligible marine renewable energy projects, including offshore wind.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com