Van Oord Finishes 111 Monopile Installations at Baltica 2
Van Oord has finished installing 111 monopiles for the 1.5GW Baltica 2 offshore wind farm in Poland, completing the project’s foundation installation scope.

Van Oord has finished installing 111 monopiles for the 1.5GW Baltica 2 offshore wind farm in Poland, completing the project’s foundation installation scope.

Ørsted expects three offshore wind projects totalling 2.5 GW to be commissioned in the second half of 2026 as construction advances across its offshore portfolio.

Steelwind Nordenham has completed 34 monopiles for the 1.5 GW Baltica 2 offshore wind farm, including units measuring about 102 m and weighing up to 1,884 tonnes.

Van Oord has installed the first monopile foundations at the 1.5 GW Baltica 2 offshore wind farm in the Polish Baltic Sea.

Baltic Towers signed a tower supply agreement with Siemens Gamesa for Poland’s Baltica 2 offshore wind project, a 1.5 GW development backed by PGE Polska Grupa Energetyczna and Ørsted.

Novastar Energy Holdings, owned by HEA Energy, won a 14-month jack-up contract for Poland’s 1.5 GW Baltica 2 project to support offshore substation commissioning with accommodation, access and crane services.

EEW SPC has loaded out the first monopiles for the Baltica 2 offshore wind project and will supply 77 monopile foundations from Rostock harbour in line with the project’s construction schedule.

BOKA Falcon has completed the first seabed preparation phase for Baltica 2, removing boulders and preparing to return with the Megalodon trenching tool for the next stage.