The first 10 Nordseecluster B monopiles have been unloaded in Eemshaven, the Netherlands, ahead of offshore construction at the 900 MW wind farm in German waters.
Project developer RWE confirmed the completion of unloading on 23 November 2026. The foundations, supplied by Chinese manufacturer Dajin Heavy Industry, weigh approximately 1,350 tonnes each and have an average length of 81 metres.
The heavy-lift terminal operated by Buss Ports will handle all 60 monopiles allocated to Nordseecluster B during 2026 and 2027. Eemshaven will provide the storage areas and port infrastructure required for the foundation installation campaign.
Production of the foundations is divided between two of Dajin Heavy Industry’s manufacturing bases in China. Tangshan will supply 50 monopiles together with 30 main access platforms, while Penglai will produce the remaining 10 monopiles.
In an earlier announcement on 3 October, Dajin Heavy Industry reported that its first consignment had departed Tangshan the previous day, bound for Eemshaven with 10 monopiles and 10 main access platforms.
The manufacturer subsequently announced on 12 October that its second consignment of 10 monopiles was being transported to Eemshaven aboard the 40,000 DWT deck carrier KING THREE. The vessel’s maiden voyage marked the entry into operation of the third and final vessel in the company’s KING series.
RWE did not identify the vessel responsible for delivering the foundations covered by its latest unloading announcement.
Installation of the monopiles at Nordseecluster B is due to start in 2027. Offshore turbine installation will follow in 2028, covering 60 units, with commercial operation scheduled to commence in early 2029.
The wind farm is the second phase of the Nordseecluster development, situated around 50 kilometres north of Juist in the German North Sea. The 660 MW Nordseecluster A is scheduled to become fully operational in early 2027.
The two phases will provide approximately 1.6 GW of generating capacity. RWE, which holds a 51% stake in the development, oversees project construction and will manage its subsequent operation. Norges Bank Investment Management holds the other 49%.