Heerema Marine Contractors has reached the keel-laying stage of its H-731 float-over barge at CIMC Sinopacific Offshore & Engineering (CIMC SOE) in Daishan, China, advancing construction of a vessel designed to install offshore converter station topsides weighing more than 30,000 tonnes.
The construction milestone was marked on 12 November 2026, approximately 11 months after the first steel was cut on 11 December 2025.
The purpose-built barge will support offshore installation work under TenneT‘s 2 GW offshore grid programme in the North Sea. Delivery is scheduled for the second quarter of 2027, with the vessel expected to begin installation operations in 2028.
According to Heerema’s published specifications, H-731 will measure 222.5 metres in length, with a width of 46.0 to 70.1 metres and a moulded depth of 15.0 metres.
The barge is designed to accommodate topsides weighing up to 40,000 tonnes during float-over installation, allowing large integrated offshore converter structures to be positioned onto their supporting foundations.
The float-over method involves transporting a topside on a barge, positioning it above the offshore support structure and transferring its weight onto the foundations through a controlled installation operation.
The project follows a framework agreement secured by Heerema in May 2023 for transportation and installation work under TenneT’s offshore grid programme.
TenneT awarded framework agreements to Heerema and Allseas covering at least 28 transportation and installation packages involving offshore jackets and topsides. Heerema was allocated approximately 60% of the available packages, without those awards being assigned to specific 2 GW projects at the time.
In January 2025, Heerema announced a separate contract with TenneT for the new float-over barge, specifically intended to handle converter station topsides exceeding 30,000 tonnes.
TenneT’s wider programme involves multiple high-voltage direct current (HVDC) offshore grid connections in German and Dutch North Sea waters, each designed to transmit 2 GW of offshore wind-generated electricity to onshore networks.
The offshore installation preparations will also involve Mammoet, which has secured a contract from Heerema covering two large topsides.
Under the Mammoet agreement, hydraulic skid shoes will transfer the topsides from a heavy transport vessel (HTV) onto H-731.
Mammoet will then use its Mega Jack System to raise each topside to the required float-over height. A deck support frame will be positioned beneath the structure before its subsequent offshore installation onto the jacket foundations.
The skidding, jacking and support-frame operations form part of the preparation work for the two topsides covered by Mammoet’s contract.