Mammoet completes Munin topside heavy lift work for Aibel
Mammoet has completed heavy lift, load-in and load-out work for the Munin topside being delivered by Aibel for Aker BP’s Yggdrasil development.

Mammoet has completed heavy lift, load-in and load-out work for the Munin topside being delivered by Aibel for Aker BP’s Yggdrasil development.

Jumbo Maritime’s Fairplayer discharged three project cargo modules in Rotterdam, including a 280 tonnes unit transferred directly onto a barge using two 900 tonnes cranes.

Haizea Wind Group has delivered 11 m-diameter monopiles from the Port of Bilbao to Ørsted for the 2.9 GW Hornsea 3 offshore wind project in the North Sea.

Mammoet is moving 122 m, 2,473 t offshore wind monopiles at Port of Argentia using a custom transport system developed for large-diameter foundations.

Mammoet used its XXL monopile transport system and MTC 1600 cranes to support Van Oord’s Baltic Power marshalling campaign, handling 78 monopiles weighing up to 1,680 tonnes.

Mammoet has loaded out a 6,892t jacket for Saipem at Arbatax, Sardinia, using 300 axle lines of SPMTs to transfer the structure onto the Castoro XI barge for the Neptun Deep project.

Mammoet helped remove the 2,300 tonne US 181 Harbor Bridge center span in Corpus Christi by lowering it onto a barge in one piece.

Mammoet completed the 33,000 tonnes Scarborough topsides load out in China using its integrated Mega Jack lifting and weighing system to streamline heavy transport work.

Mammoet supported Allseas in the 2025 load-in of the Heather Alpha and Eider Alpha topsides, completing both floating operations in a single shift after integrated preparation of Iron Lady for the two structures.