Rosetti Marino has secured a Sabratha platform EPCI contract worth more than €400 million from Mellitah Oil & Gas to upgrade the existing offshore gas production facility in Libya for the Structure A development.
The contract, announced on 12 November 2026, was awarded by Mellitah Oil & Gas BV – Libyan Branch, a joint venture between Libya’s National Oil Corporation (NOC) and Eni North Africa.
The engineering, procurement, construction and installation (EPCI) package will prepare Sabratha to receive gas from the new WHP-A wellhead platform, which is under construction through a separate contract. Once the Structure A development is completed, WHP-A will also be remotely controlled from Sabratha.
According to Rosetti Marino’s official announcement, the scope includes new modules and extensions to existing facilities, incorporating a slug catcher, chemical injection units and pig traps.
The contractor will also deliver a riser bundle approximately 200 metres long, together with the prefabrication and installation of piping, electrical connections and instrumentation required to integrate the new equipment with Sabratha’s existing systems.
Rosetti Marino previously secured a separate contract in June 2024, working alongside Kerry Project Logistics and Gruppo Antonini, for the engineering, procurement, construction and load-out of the approximately 6,000-tonne WHP-A topside.
The latest award covers modifications to the receiving Sabratha platform rather than construction of the WHP-A topside itself.
Engineering and prefabrication for the new contract will be carried out in Italy. Offshore construction and installation will involve an approximately 18-month campaign, with Rosetti Marino responsible for coordinating the marine logistics and vessels required for offshore execution.
Work is scheduled to begin immediately, with completion expected in March 2029.
Sabratha serves the Bahr Essalam gas field offshore Libya, where Eni and NOC have separately completed an upgrade to the platform’s gas compression facilities.
In June 2026, the partners announced the start-up of the Sabratha Compression Project, which involved installing a 1,600-tonne compression module with a total capacity of approximately 440 million standard cubic feet per day.
Eni said the compression project was designed to maintain gas recovery as reservoir pressure declines, enabling approximately 800 million cubic metres of additional annual gas production and associated condensate.
The new Structure A connection works are separate from the completed compression project and will allow gas from WHP-A to enter the existing Sabratha production infrastructure.