Ørsted Targets 2026 Commissioning for Three Offshore Wind Projects

Ørsted expects three offshore wind projects totalling 2.5 GW to be commissioned in the second half of 2026 as construction advances across its offshore portfolio.
Photo credit: Ørsted

SHARE ARTICLE

Ørsted expects three offshore wind projects with a combined capacity of 2.5 GW to be commissioned in the second half of 2026, according to its interim financial report for the first half of the year.

Borkum Riffgrund 3 in Germany was more than 99% complete at the end of June. Almost all turbines had been commissioned, with the remaining work continuing ahead of planned commissioning in the third quarter of 2026.

In Taiwan, Greater Changhua 2b and 4 had reached approximately 85% completion. All turbines at Greater Changhua 4 had been commissioned, while completion of the export cable installation for Greater Changhua 2b was approaching. Ørsted expects the combined project to be commissioned in the third quarter of 2026.

Revolution Wind in the US was more than 95% complete. Installation had reached 61 of the project’s 65 turbines, and commissioning activities were underway. The project is scheduled for commissioning in the second half of 2026.

Construction is also advancing at Sunrise Wind, where overall completion stood at 50% at the end of June. Foundations had been installed at 77 of 84 positions, while 20 turbines were in place. Turbine commissioning is expected to begin in the second half of 2026, followed by full commissioning in the second half of 2027.

At Baltica 2 in Poland, foundations had been installed at 103 of the project’s 111 foundation positions. Monopile installation for the offshore substations was complete, while fabrication of the four offshore substations was continuing.

Hornsea 3 in the UK was approximately 30% complete. During the first half of 2026, 43 monopiles were installed as offshore foundation and export cable activities progressed. Ørsted was also working with the grid operator on reinforcement work required for the project’s onshore grid connection.

Hornsea 3 is scheduled for commissioning in the fourth quarter of 2027 or the first quarter of 2028.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Boskalis reported lower revenue and earnings in H1 2026, while Offshore Energy remained a major contributor and the order book stood at EUR 6.8 billion.
Sif has completed the final monopile load-out for the 1.44 GW Bałtyk 2 and 3 offshore wind farms in Poland, where Heerema Marine Contractors’ Thialf is installing foundations.
CoreMarine has completed the removal of Golar LNG’s Hilli Episeyo FLNG off Cameroon ahead of upgrades in Singapore and its planned redeployment to Argentina.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com