Sofia Wind Farm Installs 80 Turbines

The Sofia offshore wind farm has installed 80 of its 100 turbines on Dogger Bank, advancing the 1.4 GW North Sea project toward planned start-up in 2025.
Image source: RWE

SHARE ARTICLE

The Sofia offshore wind farm has completed the installation of 80 wind turbines at its site on Dogger Bank in the central North Sea, moving the 1.4 GW project closer to start-up.

The development will use 100 Siemens Gamesa SG 14-222 DD turbines in total. When all units are in place, the project will have a total capacity of 1.4 GW.

Installation work is being carried out by Wind Peak, the vessel operated by Cadeler. The ship installed the first turbine in March 2025 and is transporting components for six turbines on each voyage from Hull. IWS Seawalker, a service operation vessel, is supporting the offshore campaign.

Each turbine extends more than 252 m above sea level. The blades measure 108 m and sweep about 39,000 square metres. Half of the turbines at the site use recyclable blades, and all of those units were installed in 2025.

Owned by RWE, the Sofia offshore wind farm is due to enter service in 2025. Once fully operational, the project will be able to generate enough electricity to meet the equivalent demand of 1.2 million UK homes.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Pioneering Spirit used its jacket lift system to install both suction bucket foundations and topsides in shallow water for 50Hertz’s OST-6-1 connection, completing the work in one offshore campaign.
Dogger Bank A has secured an eight-month extension to the CfD start date for its first 300 MW contract tranche. The revised July 2027 deadline follows turbine blade failures and additional repair requirements.
Sven Utermöhlen brings 20 years of offshore wind experience to Esvagt. RWE’s succession announcement also provided for him to advise its offshore wind business for six to twelve months after his departure.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com