Vineyard Wind Sues GE Vernova Over Contract Exit

Vineyard Wind has sued GE Vernova in Boston to stop the turbine supplier from terminating contracts tied to the 806 MW Vineyard Wind 1 project, as both sides dispute withheld payments, performance issues and liability linked to the blade failure.
Image source: Vineyard Wind

SHARE ARTICLE

Vineyard Wind has filed a lawsuit against GE Vernova in a Boston state court to stop the turbine supplier from ending its contracts and leaving the Vineyard Wind 1 offshore wind project off Massachusetts.

The dispute involves a turbine supply and service agreement worth about $1.3 billion. The contract covers the design, manufacture, installation and maintenance of wind turbine generators for the offshore wind farm.

Vineyard Wind 1 is located about 24 km south of Nantucket, Massachusetts. The 806 MW project uses 62 GE Vernova Haliade-X 13 MW turbines. Turbine installation started in September 2023, and the project began supplying electricity to the grid in early 2024. Later in 2024, the wind farm suffered a blade failure on one turbine. The last of the 62 turbines was installed in March, and the project is now operating partially.

According to the lawsuit, GE Vernova told the developer it would terminate the contracts at the end of April. Vineyard Wind is seeking an injunction to require the supplier to continue working on the project.

GE Vernova says Vineyard Wind withheld payment for completed work and that this gives the company grounds to terminate the contracts. Vineyard Wind argues it was entitled to withhold about $308 million because of what it described as poor performance by the turbine supplier, including issues related to the turbines.

The developer also claims GE Vernova remains liable for higher damages linked to the blade incident, with the amount reaching up to $545 million. In the lawsuit, Vineyard Wind says the supplier is the only practical company able to complete the remaining work, making a replacement unrealistic at this stage.

For its part, GE Vernova says it acted within its contractual rights and will defend its position in court. The company also says it has met its obligations, including completing turbine installation at the site.

A hearing on the preliminary injunction requested by Vineyard Wind is scheduled for 16 April.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Pioneering Spirit used its jacket lift system to install both suction bucket foundations and topsides in shallow water for 50Hertz’s OST-6-1 connection, completing the work in one offshore campaign.
Dogger Bank A has secured an eight-month extension to the CfD start date for its first 300 MW contract tranche. The revised July 2027 deadline follows turbine blade failures and additional repair requirements.
Sven Utermöhlen brings 20 years of offshore wind experience to Esvagt. RWE’s succession announcement also provided for him to advise its offshore wind business for six to twelve months after his departure.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com