The Berwick Bank B vessel fleet planned by Seaway7 comprises Seaway Alfa Lift, Seaway Strashnov and Seaway Phoenix. Subsea7’s third-quarter presentation lists 2029 and 2030 as the expected offshore work years for SSE Renewables’ planned 1.4 GW project.
In October, SSE selected Seaway7 as preferred supplier for the project’s engineering, procurement, construction and installation (EPCI) package. The proposed scope includes design, supply and offshore installation of about 90 fixed-bottom turbine foundations, alongside inter-array cables.
Berwick Bank B is part of the wider 4.1 GW Berwick Bank development. The site is in the outer Firth of Forth, about 38 km off the Scottish Borders, at an average water depth of around 52 m. SSE expects the completed project to be the world’s deepest fixed-bottom offshore wind farm.
SSE says preparatory offshore work could start in 2028. Foundation and cable installation is expected to begin in 2029 and continue into 2031. The company expects a final investment decision in late 2027.