Swire Projects delivered 30 wind turbine sets in four voyages

Reported in February 2026, the transport campaign involved four Chinese loading ports and a single discharge location in Western Australia, supporting the expansion of Warradarge to 283 MW.
Photo source: Swire Shipping

SHARE ARTICLE

Swire Projects completed a four-voyage transport campaign carrying 30 wind turbine sets from China to Western Australia for the Warradarge Stage 2 Wind Farm expansion. The shipment programme was reported in February 2026.

Cargo was loaded at Tianjin, Taicang, Nantong and Dongzao, with all four voyages delivering equipment to Henderson in Western Australia.

The use of multiple loading ports required coordination of shipping schedules to maintain consistency throughout the transport campaign.

The shipments supported the installation of 30 additional turbines at the onshore wind farm north of Perth. The turbines have a rotor diameter of 136 metres, a hub height of 84 metres and a maximum blade tip height of 152 metres, consistent with the existing units at the facility.

After discharge at Henderson, major turbine components were transported by road to the wind farm site via the Brand Highway.

The expansion will increase Warradarge’s installed generating capacity from 180 MW to 283 MW, with electricity production equivalent to the requirements of approximately 164,000 households.

According to Bright Energy Investments, all 30 additional turbines have been installed and commissioning activities are under way. The expanded wind farm is expected to become operational in early 2027.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The 38,000-dwt newbuild is the second in a four-vessel series built by ZPMC, featuring 5,066 square metres of cargo deck space and a maximum tandem lifting capacity of 700 tonnes.
The 75,000 dwt newbuilding is due for delivery in the first quarter of 2029, with an option for a second vessel that could bring the reported contract value to approximately $380 million.
The crane, rated to lift 1,800 tonnes, left Rotterdam on 22 November aboard Seaway Hawk and is due at Luba, Equatorial Guinea, on 10 December, with Cameroon as its final destination.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com