Kansai Electric Power signs deal for 40% stake in BC-Wind

The 390 MW Polish offshore wind development is under construction, with foundation installation planned for the first half of 2027 and electricity generation expected in 2028.
Photo source: Ocean Winds

SHARE ARTICLE

Japan’s Kansai Electric Power has signed an agreement to acquire a 40% stake in BC-Wind, a 390 MW offshore wind farm under construction in the Polish Baltic Sea. The investment will mark the Japanese utility’s entry into Poland’s energy market.

Under the agreement signed on 19 November 2026, the acquisition will be made through KPIC Netherlands B.V., a wholly owned subsidiary of the Japanese utility. Ocean Winds, which currently holds the entire share capital of project company C-Wind Polska, will retain a 60% interest after the transaction closes.

The investment is expected to bring Kansai Electric Power’s overseas power generation portfolio to approximately 2,654 MW on an equity ownership basis. The company plans to use its participation in BC-Wind to develop expertise applicable to renewable energy projects in Japan and other international markets.

BC-Wind reached a final investment decision in December 2025, with approximately €2 billion in project financing secured. The development also holds a contract for difference awarded during the initial phase of Poland’s offshore wind programme.

Construction preparations are progressing across several major work packages. Dajin Heavy Industry is responsible for manufacturing 26 turbine monopiles and an additional monopile for the offshore substation. The initial shipment of monopiles arrived at Świnoujście Offshore Terminal on 28 October 2026.

Offshore foundation installation is planned for the first half of 2027. DEME will carry out foundation installation and the laying of inter-array and export cables, with Cadeler contracted to install the wind turbines in 2028.

Situated within Poland’s exclusive economic zone, approximately 23 kilometres off the Pomeranian coast, BC-Wind will use 26 turbines from Siemens Gamesa. Each unit has a nominal capacity of 14 MW, which can be increased to 15 MW using Power Boost technology.

Ocean Winds, an equally owned joint venture between EDP Renewables and ENGIE, expects BC-Wind to begin generating electricity in 2028.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Dajin Heavy Industry is supplying 60 monopiles for Nordseecluster B, each weighing around 1,350 tonnes, with Buss Ports handling the foundations ahead of offshore installation in 2027.
Arabian Drilling has secured 10- and 15-year commitments for two self-propelled offshore service units with Khafji Joint Operations, lifting its contracted backlog to a record SAR 18.5 billion.
Vår Energi has agreed to acquire ConocoPhillips’ Norwegian business, including Greater Ekofisk operatorship and its Teesside terminal interest. Completion is expected in Q1 2027, subject to approvals.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com