South Korea’s 364.8 MW Yeonggwang Nakwol offshore wind farm has entered full commercial operation, with electricity sales now covering its entire installed capacity following the completion of final electrical safety testing.
According to a regulatory announcement issued by B.Grimm Power on 18 November 2026, the project passed its continuous energisation test on 17 November and received certification from the Korea Electrical Safety Corporation (KESCO) on the same day. Electricity sales covering the full 364.8 MW installed capacity commenced on 18 November.
Located off Yeonggwang County in South Jeolla Province, the wind farm comprises 64 turbines rated at 5.7 MW each. It is operated by Nakwol Blueheart, in which B.Grimm Power Korea holds a 49% equity interest.
According to B.Grimm Power, Yeonggwang Nakwol is now South Korea’s largest single offshore wind farm to have reached full commercial operation. Its installed capacity exceeds the approximately 352 MW combined capacity of the country’s other offshore wind farms that had previously entered commercial operation.
The development reached this stage following the completion of its offshore construction and installation programme. Turbine installation began in 2025, and the project generated its first electricity in December that year.
All 64 monopile foundations were installed by June 2026. GS Entec and Sif supplied the foundations, while Samhae ENC carried out the installation works. The final Vensys 5.7 MW wind turbine was installed on 17 October 2026.
The project has a 20-year renewable energy certificate (REC) sale and purchase agreement with Korea Southern Power (KOSPO), covering generation from the wind farm’s entire installed capacity.
The agreement sets a fixed combined settlement price of KRW 307.144 per kWh, incorporating the electricity system marginal price (SMP) and the REC component calculated using the applicable weighting factor.
Although electricity sales have started across the project’s installed capacity, the 20-year REC contract period will begin only after the Korea Power Exchange (KPX) completes its final system inspection, scheduled for December 2026.
Until then, the project can recognise revenue from electricity and REC sales at the agreed combined rate without reducing the subsequent 20-year contract period.
B.Grimm Power said the project was developed with Korean partner Myungwoon Industrial Development, with participation from more than 100 South Korean companies.