Xiang He Kou completes Seminole float-off in Bonny

Xiang He Kou completed the Seminole float-off in Bonny after carrying the vessel and two support units from Bahía Blanca. COSCO lists a 177.6-by-43-metre cargo deck and 13 metres of submersion.
Photo courtesy of Cosco Shipping Heavy Transport

SHARE ARTICLE

The semi-submersible heavy transport vessel Xiang He Kou completed the float-off in Bonny, Nigeria, of Micoperi’s derrick lay vessel Seminole and two offshore support vessels, which it had carried from Bahía Blanca, Argentina.

COSCO lists Xiang He Kou as a 48,480-tonne deadweight semi-submersible heavy-lift vessel. It is 216.7 metres long and has a 177.6-by-43-metre cargo deck with a deck-submersion capability of 13 metres. COSCO also lists float-on/float-off among the vessel’s capabilities. During the Bonny operation, the transport vessel was ballasted and submerged to allow the cargo to be manoeuvred off its deck.

Micoperi describes Seminole as a self-propelled derrick lay vessel combining pipe-laying and lifting functions. It measures 135.81 metres long and 30.5 metres wide. Its specifications list a pipe-tensioning capacity of 200 tonnes and a 703-tonne revolving crane. Built in France in 1975, the vessel underwent a major rebuild completed in 2011.

Before the shipment to Nigeria, Seminole and the two support vessels had worked on the submarine pipeline section of Argentina’s Vaca Muerta Oil Sur (VMOS) project. ArgenPorts identified the accompanying units as Spring360 and EDT Aeolus, and reported that the three vessels were loaded onto Xiang He Kou at Bahía Blanca for the onward journey to Nigeria.

The shipment brings Seminole back to Nigeria after an earlier Bonny-to-Bahía Blanca voyage. HMT News previously reported that White Marlin carried Seminole and two tugs from Bonny to Argentina.

Photo courtesy of Cosco Shipping Heavy Transport
Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The 75,000 dwt newbuilding is due for delivery in the first quarter of 2029, with an option for a second vessel that could bring the reported contract value to approximately $380 million.
The crane, rated to lift 1,800 tonnes, left Rotterdam on 22 November aboard Seaway Hawk and is due at Luba, Equatorial Guinea, on 10 December, with Cameroon as its final destination.
Dajin Heavy Industry is supplying 60 monopiles for Nordseecluster B, each weighing around 1,350 tonnes, with Buss Ports handling the foundations ahead of offshore installation in 2027.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com