Dogger Bank A CfD Start Date Extended to July 2027 Amid Turbine Repairs

Dogger Bank A has secured an eight-month extension to the CfD start date for its first 300 MW contract tranche. The revised July 2027 deadline follows turbine blade failures and additional repair requirements.
Photo source: Dogger Bank Wind Farm

SHARE ARTICLE

SSE, Equinor and Vårgrønn have received an eight-month extension to the Contracts for Difference (CfD) start date for part of the 1.2 GW Dogger Bank A offshore wind farm in the UK, as turbine repairs continue to delay commissioning.

The Low Carbon Contracts Company (LCCC) has approved a revised CfD start date of 31 July 2027 for the project’s first 300 MW contract tranche, awarded under Allocation Round 3 (AR3). The previous contractual deadline was 30 November 2026.

The developers are understood to have advised LCCC that Dogger Bank A would be unable to meet the commissioning milestones and minimum generating capacity requirements needed to activate the contract by the original deadline.

The revised schedule follows construction difficulties in 2024, including two blade failures involving GE Vernova Haliade-X turbines. The incidents prompted further inspections, which identified additional repair requirements across the wind farm.

The project experienced blade damage incidents in May and August 2024. Following the August incident, the project team reported that GE Vernova’s investigation had linked the failure to conditions encountered during turbine commissioning.

More than ten turbines are understood to require replacement blades and work on certain nacelle components. The two turbines affected by the earlier blade failures are also expected to receive replacement towers, nacelles and blades.

These repairs have added to the commissioning workload at Dogger Bank A, which was originally scheduled for completion in 2024.

The 95-turbine Dogger Bank A project, located approximately 130 km off the UK coast, is now expected to become fully operational in the third quarter of 2027, according to the latest SSE energy market disclosure cited in the report.

Despite the extended timetable, the developers maintain that the wind farm will be substantially available for electricity generation by the end of 2026.

A project spokesperson attributed the CfD extension to the continuing effects of the 2024 construction setbacks and their impact on commissioning. The developers indicated that the revised timetable was consistent with delays previously communicated to the market.

The commissioning difficulties described have affected Dogger Bank A only.

The extension applies to the first 300 MW CfD tranche. No changes have been reported for the remaining two contract tranches, which retain their existing long-stop dates of 31 January and 31 May 2027, respectively.

The revised CfD date does not represent a new target for the wind farm’s first electricity generation. It concerns the contractual requirements for bringing the first 300 MW CfD tranche into effect, while turbine repairs and commissioning continue.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Aibel will assign around 250 employees in Asker, supported from Haugesund, to the study, with completion expected in late 2027. An exclusive EPma option is included; fabrication will be awarded later.
Sven Utermöhlen brings 20 years of offshore wind experience to Esvagt. RWE’s succession announcement also provided for him to advise its offshore wind business for six to twelve months after his departure.
Shenhai Hydrogen Energy No. 1 is preparing for South China Sea deployment, with PEM electrolysis, three types of hydrogen storage and a disconnectable mooring system designed for shallow waters.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com