Hanwha Ocean has decided not to participate in an 800 MW offshore wind project planned in waters off Buan County in South Korea’s Jeonbuk Province.
According to a regulatory filing dated 25 November 2026, cited by South Korean media, the shipbuilder reached its final decision following a comprehensive review of the development conditions. No specific reason for its withdrawal was disclosed.
The decision concludes a period of uncertainty over Hanwha Ocean‘s participation, following several regulatory disclosures issued since July indicating that its involvement had yet to be finalised.
The proposed wind farm, known as Jeonbuk Southwest Offshore Wind Expansion Complex 1, represents the initial phase of a broader 2.4 GW offshore wind development programme.
A consortium led by Korea Hydro & Nuclear Power (KHNP) was selected as the preferred bidder on 25 June 2026. Other participants include Korea East-West Power, KEPCO Engineering & Construction, KEPCO KPS, Doosan Enerbility and Samil C&S.
According to Seoul Economic Daily, the estimated investment required for the 800 MW development has increased from KRW 4.8 trillion to around KRW 6 trillion, reflecting rising equipment and construction costs.
The reported increase in project costs was not identified in the regulatory disclosure as the reason for Hanwha Ocean‘s decision.
Construction of the wind farm is scheduled to begin in the second half of 2028, with completion targeted for 2030.