Petronas names third FLNG unit PFLNG TIGA at Samsung Heavy Industries

The 2 MTPA PFLNG TIGA is scheduled to depart Geoje in February 2027 for Sipitang, Sabah, where hook-up and commissioning will precede commercial operations targeted for the third quarter of 2027.
Floating FLNG TIGA (Source: Petronas)

SHARE ARTICLE

Malaysian energy group Petronas held a naming ceremony for its third floating liquefied natural gas (FLNG) facility, PFLNG TIGA, on 24 November 2026 at the Geoje shipyard of Samsung Heavy Industries (SHI) in South Korea.

With construction still underway, the facility is designed to produce 2 million tonnes of LNG annually. It measures 281 metres in length, 64 metres in breadth and 32 metres in depth. Petronas describes the unit as the world’s first nearshore FLNG facility.

The engineering, procurement, construction and commissioning (EPCC) project is being undertaken by a consortium led by Japan’s JGC Corporation, with SHI among its members.

JGC Corporation is responsible for topsides engineering, equipment procurement and commissioning, the full EPCC scope for associated onshore facilities, and overall project management. SHI handles the hull EPC scope and topsides module fabrication.

The facility features 11 major modules housing approximately 40,000 tonnes of topsides equipment.

According to JGC Corporation, the project is progressing as planned, with sail-away from Geoje scheduled for February 2027. Petronas indicated that departure would depend on the completion of systems integration, testing and preparations for the voyage.

The nearshore FLNG facility will be deployed to the Sipitang Oil and Gas Industrial Park in Sabah, Malaysia. Upon arrival, the unit will be moored alongside a jetty and connected to the onshore electricity supply and an approximately 12-kilometre feed gas pipeline.

Following hook-up and system commissioning, feed gas will be introduced to initiate liquefaction and gradually increase LNG production. Petronas is targeting commercial operations in the third quarter of 2027 and plans to sell its initial LNG cargoes on the spot market.

JGC Corporation previously worked on Petronas‘ second FLNG facility, PFLNG DUA, which was completed in 2021.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Spain has activated its level-two maritime pollution contingency plan over the vessel's estimated cargo of 7,000 tonnes of diesel, with no visible pollution reported during the initial survey.
The shipbuilder has decided against participating in the KHNP-led development after months of uncertainty, while local media report that estimated project costs have risen to KRW 6 trillion.
The 38,000-dwt newbuild is the second in a four-vessel series built by ZPMC, featuring 5,066 square metres of cargo deck space and a maximum tandem lifting capacity of 700 tonnes.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com