The MV Luisa transport campaign is being prepared in Bilbao ahead of a planned 50-week monopile movement programme. According to the campaign update, eight cargo saddles have been installed aboard the semi-submersible heavy transport vessel, while 72 axle lines of SPMTs are standing by. The first load-out is scheduled for Monday.
The Port of Bilbao’s vessel bulletin listed MV Luisa as arriving from Rotterdam on 22 November and scheduled to depart for Vlissingen on 24 November.
Norfolk Vanguard West remains a possible project link. Haizea Wind Group has confirmed that it is manufacturing monopiles for the project at its Bilbao facilities.
MV Luisa is a semi-submersible deck carrier built in 2008. SAL Heavy Lift’s fleet list gives the vessel an overall length of 174 m, a beam of 48 m and 7,104 m² of free deck space. It lists a uniform deck load of 18 t/m², a maximum submerged draught of 15.29 m and a service speed of 9 knots.