Hyundai Engineering & Construction (Hyundai E&C) plans to submit a priced engineering, procurement and construction (EPC) proposal in December 2026 for the 532-megawatt Anma offshore wind project off Yeonggwang, South Jeolla Province, ChosunBiz reported on 18 November 2026, citing energy and construction industry sources. The proposal would make Hyundai E&C responsible for EPC delivery under a completion guarantee. The report describes a planned proposal; it does not say that an EPC contract has been awarded.
The project is planned about 40 kilometres off Yeonggwang. Its project overview gives its capacity as 532 MW, while a Korea Power Exchange listing specifies 38 turbines rated at 14 MW each. The developer says Anma was selected in the government’s 2024 fixed-price contract auction.
ChosunBiz reported that permitting and commercial challenges have held up the project for years. The proposed site overlaps a military operations zone, requiring coordination with the Ministry of National Defense; the report said that coordination was reportedly resolved through measures including additional radar installations. Higher interest rates and exchange rates also increased costs, making the project’s contracted power sales price harder to sustain.
Financing and supplier issues added to the delays. Equis, the project’s largest shareholder, pledged its 78% stake as collateral for overseas loans and decided to sell part of its holding. Copenhagen Infrastructure Partners (CIP), which had carried out due diligence for seven to eight months to acquire the stake, abandoned the acquisition in late April 2026.
Meanwhile, turbine supplier Siemens Gamesa withdrew after its contract expired. LS Cable & System and LS Marine Solution terminated a subsea cable contract worth KRW 271.1 billion, while SK oceanplant paused substructure deliveries pending project normalization, according to the report.
The developer and Equis asked Hyundai E&C to participate, ChosunBiz reported. A contractor willing to accept completion responsibility is needed to attract new investors and lenders. The report said construction would need to start by May 2027 to meet the project’s commercial-operation deadline. It also reported that Korea East-West Power was considering participating, although the utility was not expected to acquire all of Equis’s stake.