Hornsea 3 Turbine Installation Preparations Advance at Able Seaton Port

Ørsted is preparing Hornsea 3 turbine installation as components are marshalled at Able Seaton Port. DEME’s Norse Energi has arrived to support load-out and offshore work.
Source: Able

SHARE ARTICLE

Ørsted is preparing for Hornsea 3 turbine installation, with Siemens Gamesa components being marshalled at Able Seaton Port and DEME’s jack-up vessel Norse Energi arriving to support offshore work.

The first turbine components reached the port in July, Ocean Energy Resources reported, citing Able. Since then, Able’s heavy-lift and logistics teams have moved blades, nacelles and tower sections from the quayside into storage. Tower sections are being assembled at the port before load-out.

In an update, Able said Norse Energi had arrived at Able Seaton Port for the project. The jack-up vessel, operated by DEME, is 151 metres long, has a 62-metre beam and is equipped with a 3,200-tonne crane, according to Able. It will be used to load out and install Hornsea 3 turbine components.

The wind farm is planned to comprise 197 Siemens Gamesa SG 14-236 turbines. Ørsted says each turbine is rated at 15 MW and has three 115-metre blades. The project, located about 120 kilometres off Norfolk, is expected to have a capacity of 2.9 GW and generate enough electricity for more than 3.3 million UK homes once operational.

Offshore construction is already under way. Ørsted installed the first monopile in May, and the second offshore converter station was installed in September. The latter milestone is covered in HMT News’ report on the second offshore converter station. The turbine installation preparations follow these foundation and transmission-system works.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Sofia Wind Farm (Photo: RWE)
RWE expects power generation at its 1.4 GW Sofia offshore wind farm to resume by late November. The company attributes the onshore cable damage to a third party and plans to seek compensation.
Hornsea 3 inter-array cable installation. (Image source: Seaway7)
Seaway7's cable installation campaign at Ørsted's 2.9 GW Hornsea 3 project covers more than 536 km of 66 kV cables, with Seaway Phoenix and Seaway Moxie assigned to the offshore work.
Two bulk carriers and a tanker were boarded in the eastbound traffic lane during nighttime passages in November. One seafarer was injured, and engine spare parts were stolen from two vessels.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com