Seaway7 Lays First Inter-Array Cable at Hornsea 3

Seaway7's cable installation campaign at Ørsted's 2.9 GW Hornsea 3 project covers more than 536 km of 66 kV cables, with Seaway Phoenix and Seaway Moxie assigned to the offshore work.
Hornsea 3 inter-array cable installation. (Image source: Seaway7)
Image source: Seaway7

SHARE ARTICLE

Seaway7 has installed the first inter-array cable at Ørsted’s Hornsea 3 offshore wind farm in the UK North Sea, beginning its offshore cable installation campaign at the 2.9 GW project.

The company confirmed the installation in a LinkedIn update, stating that its scope covers the transportation and installation of more than 536 km of 66 kV inter-array cables. The cables will connect the wind turbines to the project’s two offshore converter stations.

The installation campaign involves the cable-laying vessel Seaway Phoenix and the installation support vessel Seaway Moxie, according to Seaway7’s official project information.

Ørsted awarded the transportation and installation contract to Seaway7 in October 2024. The work forms part of the construction of Hornsea 3, which is located approximately 120–160 km off the Yorkshire and Norfolk coasts and will comprise 197 offshore wind turbines.

According to OffshoreWind.biz, Hellenic Cables and Prysmian are supplying the inter-array cables, while JDR Cable Systems is responsible for cable testing and termination.

The installation follows preparations reported in October, when Seaway Phoenix was loading cables at Eemshaven in the Netherlands ahead of its planned deployment to the wind farm. Seaway Moxie was also preparing to mobilise for the offshore work.

Hornsea 3’s two offshore converter stations were installed earlier this year. In September, Heerema Marine Contractors completed installation of the second station using its semi-submersible crane vessel Sleipnir, as previously reported by HMT News.

The latest campaign continues Seaway7‘s involvement in the Hornsea offshore wind developments. The company previously transported and installed approximately 170 km of inter-array cables at Hornsea 1 and 382 km at Hornsea 2.

Seaway7 is now undertaking the inter-array cable installation programme for the third project in the Hornsea zone, with its installation vessels assigned to connect the wind turbines to the offshore transmission infrastructure.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Ørsted is preparing Hornsea 3 turbine installation as components are marshalled at Able Seaton Port. DEME’s Norse Energi has arrived to support load-out and offshore work.
Sofia Wind Farm (Photo: RWE)
RWE expects power generation at its 1.4 GW Sofia offshore wind farm to resume by late November. The company attributes the onshore cable damage to a third party and plans to seek compensation.
Sif will close one Maasvlakte 2 production line and reduce operations in Roermond as it seeks bridge financing while a 190 kton offshore wind project awaits its client’s final investment decision.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com