Finland’s first offshore wind tender in its exclusive economic zone (EEZ) could begin in the first half of 2027 after the government designated four areas in the Bothnian Sea and Bothnian Bay for development.
The decision, announced on 5 November 2026, establishes two potential development areas in each sea. Bothnian Bay South (Perämeri etelä) will be offered first, while tendering for the remaining three areas will follow at a later stage.
The other designated areas are Bothnian Bay North (Perämeri pohjoinen), Bothnian Sea East (Selkämeri itä) and Bothnian Sea West (Selkämeri länsi).
The Finnish Energy Authority will organise the competitive tenders to select a project developer for each area. According to the Finnish Government’s announcement, bids will be evaluated on the price offered and qualitative criteria, with each accounting for 50% of the overall assessment.
Successful bidders may apply to the government for an exploitation permit, allowing them to conduct more detailed offshore investigations and pursue the additional permits required for development.
The government has also introduced requirements for tendering and performance securities. The successful bidder’s performance security will increase as the project advances, starting at a relatively low level during early development. The security will be released only if the project is implemented.
The tendering framework does not include state aid. The government estimates that offshore wind projects in the EEZ could take 10 to 15 years to progress from competitive tendering to electricity generation.
Separately, the government has proposed amendments to the Water Act covering offshore wind construction, decommissioning obligations and financial security requirements.
The new offshore wind decree (971/2026), issued on 5 November and published on 9 November 2026, is scheduled to enter into force on 1 December 2026. It provides detailed rules for the tendering process under Finland’s Act on Offshore Wind Power in the Exclusive Economic Zone (937/2024), which took effect on 1 January 2025.
Under the proposal, offshore wind installations would generally have to be dismantled completely at the end of their operational lives. However, the Finnish Supervisory Agency could assess individual projects to determine the extent of structural removal required at seabed level.
The proposed decommissioning rules would also apply to projects in Finnish territorial waters. For those developments, Metsähallitus would agree with project developers on the financial security needed to cover dismantling obligations.
The proposal would allow decommissioning security to be accumulated primarily after operations begin, while retaining developers’ responsibility for removal costs under the polluter-pays principle.
The Water Act amendments are expected to enter into force in spring 2027.