Seaway7 completes East Anglia Three cable laying campaign

Seaway7 has laid 95 inner-array cables totalling more than 240 km at the 1.4 GW wind farm, following completion of all 95 foundations. Cable testing, termination and trenching remain underway.
Photo source: Seaway7

SHARE ARTICLE

Seaway7 has completed the East Anglia Three cable laying campaign at the 1.4 GW offshore wind farm in the UK, laying 95 inner-array cables totalling more than 240 km.

The work involved loading, laying and pulling the cables into the turbine foundations. Testing, termination and trenching activities remain underway as Seaway7 progresses the remaining work under its contract.

The milestone follows the completion of all 95 monopile foundations and transition pieces in August. Seaway7 carried out the foundation installation using its jack-up vessel Seaway Ventus.

Under its 2023 contract with ScottishPower Renewables, Seaway7 is responsible for the transportation and installation of the foundations, seabed preparation, scour protection and the engineering, supply and installation of the inner-array cables.

Located approximately 69 km off the Suffolk coast, the GBP 4 billion East Anglia Three project is jointly owned by ScottishPower Renewables and Masdar.

The wind farm will feature 95 Siemens Gamesa turbines rated at 14.7 MW each, with 115-metre blades. Turbine installation is also underway, with the project expected to become fully operational by the end of 2026.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Pioneering Spirit used its jacket lift system to install both suction bucket foundations and topsides in shallow water for 50Hertz’s OST-6-1 connection, completing the work in one offshore campaign.
Dogger Bank A has secured an eight-month extension to the CfD start date for its first 300 MW contract tranche. The revised July 2027 deadline follows turbine blade failures and additional repair requirements.
Sven Utermöhlen brings 20 years of offshore wind experience to Esvagt. RWE’s succession announcement also provided for him to advise its offshore wind business for six to twelve months after his departure.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com