Subsea7 Renewables Revenue Rises 11% in Q3 2026
Subsea7’s Renewables revenue rose 11% to $336 million in Q3 2026. Vessel utilisation reached 92%, while adjusted EBITDA was $55.2 million and the group raised its full-year revenue guidance.

Subsea7’s Renewables revenue rose 11% to $336 million in Q3 2026. Vessel utilisation reached 92%, while adjusted EBITDA was $55.2 million and the group raised its full-year revenue guidance.

Seaway7 has laid 95 inner-array cables totalling more than 240 km at the 1.4 GW wind farm, following completion of all 95 foundations. Cable testing, termination and trenching remain underway.

Dogger Bank B has passed the halfway point in turbine installation, with 49 of 95 turbines installed. Seaway7’s Seaway Ventus is preparing to join Jan De Nul’s Voltaire at the UK offshore wind project.

Masdar and ScottishPower Renewables have installed all 95 foundations and transition pieces at the 1.4GW East Anglia THREE offshore wind farm off Suffolk.

Subsea 7 reported Q2 2026 net income of $254 million and Adjusted EBITDA of $471 million as its full-year margin guidance increased to approximately 24%.