CIP Completes 99 Pin Piles and Substation at Fengmiao I

CIP has completed all 99 pin piles, both export cables and the offshore substation at Taiwan’s Fengmiao I Offshore Wind Farm, which is targeting grid connection in 2027.
Photo: CIP Taiwan Round 3 Projects

SHARE ARTICLE

CIP has completed the installation of 99 pin piles and the offshore substation at the Fengmiao I Offshore Wind Farm in Taiwan.

By late July, both export cables had also been laid, buried and pulled in. The project remains on schedule for grid connection in 2027.

The offshore substation was installed by CDWE using the heavy-lift vessel Green Jade. Fengmiao I is CIP’s third offshore wind project in Taiwan and the first to feature an offshore substation.

CIP said the project includes the world’s tallest installed jacket foundation for an offshore substation.

Taiwanese suppliers and contractors are involved in several parts of the construction programme. CTCI-M and Century Group are manufacturing pin piles and wind turbine jacket foundations.

Local fishermen from Taichung have also been engaged to provide guard vessel services and marine mammal observation during construction.

Development of the Fengmiao II Offshore Wind Farm is continuing toward its targeted grid connection in 2030.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The 600 MW project’s substation contract covers engineering, procurement, fabrication, load-out, offshore hook-up, testing and commissioning of a topside, jacket and suction bucket foundations.
Northland Power expects final permits for Hai Long in the first half of 2027. Construction costs remain in line with its original estimates as the development moves towards full commercial operation.
Gennaker's OSS Zingst and OSS Darß offshore substations have departed the Netherlands for installation in the Baltic Sea. Their topsides and jackets will support 50Hertz's 927 MW OST-6-1 grid connection.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com