Seatrium Marks First FPSO Full-Scope EPCC Milestone With P-78 First Oil

Seatrium says P-78 started producing on 31 December 2025, marking a full EPCC FPSO scope that includes at-sea commissioning, before Final Acceptance by Petrobras.
PETROBRAS 78

SHARE ARTICLE

On 2 January 2026, Seatrium said P-78 began producing oil on 31 December 2025, describing the project as its first FPSO delivery completed under a full EPCC scope that also covered commissioning activities offshore. Awarded in 2021, P-78 is the first of six P-Series units being built for Brazil’s national oil company Petrobras (Petroleo Brasileiro S.A.), and the group linked the milestone to the closing stage of work leading to the customer’s Final Acceptance. Seatrium also stated this was its 37th FPSO project delivered to Petrobras.

Marlin Khiew, Executive Vice President of Seatrium Energy (Americas), attributed the schedule outcome to the One Seatrium Global Delivery Model and to cooperation with Petrobras, adding that lessons from P-78 will be applied across the remaining five P-Series projects.

The group said fabrication and integration drew on its footprint in Brazil, China, and Singapore, and that the vessel was towed to the Búzios field with major marine and production systems already in operation to enable a rapid start-up at the site.

Búzios sits in the Santos Basin around 180–230 km off Rio de Janeiro. P-78 is permanently moored in about 2,100 m water depth using spread mooring, and is designed for up to 180,000 barrels of oil per day and 7.2 million cubic metres of gas per day, with minimum crude storage of 2 million barrels.

Across P-78, P-80, P-82, P-83, P-84, and P-85, Seatrium said the series will include CCUS for CO₂ separation and reinjection, alongside thermal and waste-heat recovery and seawater deaeration. The six projects are expected to add 1.3 million barrels per day of production capacity for Brazil and to create over 60,000 jobs in communities where Seatrium’s Brazilian yards operate.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Petrobras' P-82 FPSO departed Singapore for Brazil's Búzios field on 18 October. The 225,000-bpd production unit is expected to begin operations in 2027 as the field's tenth platform.
COOEC has set 2027 as its target for a first Brazilian FPSO contract after placing second in the Albacora tender. The project has progressed to commercial negotiations between Petrobras and Yinson.
Shell has agreed to acquire 30% of Bay du Nord offshore Canada. Equinor will retain 70% and remain operator as the CAD 14 billion development moves towards an investment decision targeted for early 2027.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com