Sarens Rapidly Mobilises to Execute Load-Out of Five Modules for FPSO P-79 in Brazil

Belgian heavy-lifting specialist Sarens has swiftly executed the load-out of five major modules for FPSO P-79 at Brazil’s EBR Shipyard, showcasing exceptional mobilisation and engineering efficiency.
Sarens completes the load-out of five modules (1,400–4,000 t) for FPSO P-79 at Estaleiro EBR, Brazil. (Image: Sarens)

SHARE ARTICLE

Belgian heavy-lifting and transport specialist Sarens NV has successfully completed the load-out of five large modules destined for the FPSO P-79 at the Estaleiro EBR shipyard in São José do Norte, Brazil.

The project began following a client request on 15 March 2024, with a proposal submitted on 27 March and the contract signed by 3 April. Sarens then mobilised its fleet aboard a vessel departing on 24 June and achieved on-site presence by 1 August.

Facing a demanding schedule and challenging logistics — with the shipyard accessible only by boat or ferry and exposed to strong winds, rain, and cold weather — Sarens deployed 136 axle-lines of SPMTs (Self-Propelled Modular Trailers), 8 Power-Pack Units (PPUs) and 20 load cells to transport modules weighing between approximately 1 400 tonnes and 4 000 tonnes. The SPMTs remained on site for 45 days to complete the load-out operations.

The operation involved close collaboration among teams from Sales, Engineering, Contract Management, and Field Operations, with equipment and specialists mobilised from Norway, the UK, and Belgium.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Modules weighing around 5,000 tonnes each have been installed on the 45,000-tonne Tlaloc FPU under construction in South Korea for the Trion project.
Sarens completed lifting, weighing, transport and load-out work for Angola’s South Ndola project, including a 1,150 t jacket, pin piles and a 575 t topside.
Sarens is preparing 560 SPMT axle lines and 24 PPUs for the July 2026 load-out of the 17,666 t Valhall PWP topside in Stord after module operations across Norway.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com