
DEME Secures Zeevonk Foundation Installation Contract
DEME has secured a contract in its €150 million to €300 million category to transport and install 69 monopile foundations for the 1 GW Zeevonk offshore wind project.

DEME has secured a contract in its €150 million to €300 million category to transport and install 69 monopile foundations for the 1 GW Zeevonk offshore wind project.

Vattenfall has started offshore construction at the Nordlicht offshore wind cluster with the first monopile installation for Nordlicht I in the German North Sea.

Vattenfall has launched transition piece workflow trials in Aalborg for the Nordlicht offshore wind project, testing installation, cable work, and safety procedures before offshore construction starts in July 2026.
For general inquiries and to contact us,
please email: info@hmt-news.com