Douglas CCS Platform Installed in Liverpool Bay
Liverpool Bay CCS has installed the Douglas CCS platform, featuring a 1,885 t topside and 1,755 t jacket. The wider CO₂ transportation and storage network serving HyNet is approximately 50% complete.

Liverpool Bay CCS has installed the Douglas CCS platform, featuring a 1,885 t topside and 1,755 t jacket. The wider CO₂ transportation and storage network serving HyNet is approximately 50% complete.

Rosetti Marino has sent the Douglas CCS platform from Piombino to Liverpool Bay, where offshore installation is scheduled by the end of September under the Liverpool Bay CCS project.