Sarens Loads Out FPSO P-82 Modules at Seatrium Aracruz Yard

Sarens completed the weighing and load-out of eight FPSO P-82 modules at Seatrium’s Aracruz shipyard in Brazil, using 112 axle lines of SPMTs and 16 load cells.
Image source: Sarens

SHARE ARTICLE

Sarens has completed the weighing and load-out of eight modules for FPSO P-82 at Seatrium’s Aracruz shipyard in Brazil, using self-propelled modular transporters (SPMTs) and load cells for modules weighing up to 3,000 t.

The scope covered six major modules and two smaller units. FPSO P-82 has a production capacity of 225,000 barrels per day.

Preparations followed more than a year of technical and commercial discussions between Sarens and Seatrium, including meetings in Singapore and Brazil. Engineering work focused on shipyard constraints, ground-bearing pressures, support positions, weighing points and load-out procedures.

The first load-outs took place in September 2025, when Sarens moved modules weighing 2,600 t and 2,300 t. The operation used 112 axle lines of SPMTs and 16 load cells with capacities ranging from 200 t to 750 t.

One month later, the team weighed and loaded out two additional major modules weighing 3,000 t and 2,700 t, together with two smaller modules weighing 400 t and 200 t. In mid-November, two further modules weighing 2,700 t and 2,000 t were weighed and loaded out.

Before operations began, Sarens completed the required technical and administrative documentation, with the equipment ready for transport 24 hours ahead of schedule.

Personnel from Brazil, Belgium, Spain, Kazakhstan and Thailand took part in the project.

Sarens has also handled other FPSO module movements at Brazilian shipyards, including sites in Sao Jose do Norte and Aracruz, with modules weighing between 2,500 t and 4,000 t.

According to Sarens, Brazil’s local content requirement has led to several topside processing modules being built at Brazilian shipyards in recent years before being transported to Asia for integration with FPSO hulls. Sarens’ work has included weighing and loading these modules for transport.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
BOA completed the Wicher frigate launch in Gdynia using BOABARGE 33 after the vessel was transferred from the construction hall to the semi-submersible barge by SPMTs.
Saipem has secured a $1.8 billion EPCI contract in the Middle East covering offshore and subsea facilities, with the client and project details undisclosed.
The third Gulf of America oil and gas lease sale generated $82.7 million in high bids, with 16 companies submitting 69 bids for 59 offshore blocks.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com