Cadeler targets 12-vessel offshore wind installation fleet by mid-2027

Wind Apex is scheduled to begin work at Dogger Bank C in Q3 2027, while Cadeler has two further T-class installation vessels on order for delivery in 2030 and 2031.
Cadeler’s WTIV Wind Osprey Source: Cadeler

SHARE ARTICLE

Cadeler expects its offshore wind installation fleet to expand to 12 vessels by mid-2027, following the scheduled delivery of its third A-class newbuild, Wind Apex, in the second quarter of 2027. The company outlined the expansion plans in its third-quarter earnings release on 23 November 2026.

Wind Apex is scheduled to undertake its first assignment at the UK’s 1.2 GW Dogger Bank C offshore wind farm in the third quarter of 2027. The vessel will supplement the existing installation capacity allocated to the project’s 87-turbine transport and installation campaign.

The company currently operates a fleet of 11 vessels following the delivery of Wind Ace in July 2026. Designed to undertake both foundation and turbine installation, the A-class vessel is scheduled to make its operational debut at the East Anglia TWO offshore wind farm in 2027.

Beyond the current expansion programme, Cadeler has two T-class offshore wind installation vessels on order from COSCO Shipping Offshore. Ordered in August 2026, the vessels are scheduled for delivery in 2030 and 2031 and are intended to handle large offshore wind foundations and turbines.

The company’s reported contract backlog reached approximately €2.4 billion on 23 November 2026, including contractual options. The figure incorporates new contracts secured since the end of September but excludes deductions for work performed during that period.

Projects that have received a positive final investment decision (FID) account for 76% of the reported backlog. Vessel reservation agreements and preferred supplier agreements are excluded from the backlog calculation.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The CRPO 168 and 170 packages cover production deck manifolds, pipelines and power cables, with Saipem set to deploy its regional construction fleet and undertake fabrication in Saudi Arabia.
Windcat's second MP-ASV is due for delivery in the first quarter of 2029, with a capacity of 190 persons on board, a 150-tonne subsea crane and provision for up to 150 days offshore.
ExxonMobil’s Block 15 investment covers Kizomba A and B redevelopment and Likembe field development, while a separate exploration well has delivered the concession’s 21st hydrocarbon discovery.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com