Sarens Prepares 17,666 t Valhall PWP Topside Load-Out
Sarens is preparing 560 SPMT axle lines and 24 PPUs for the July 2026 load-out of the 17,666 t Valhall PWP topside in Stord after module operations across Norway.

Sarens is preparing 560 SPMT axle lines and 24 PPUs for the July 2026 load-out of the 17,666 t Valhall PWP topside in Stord after module operations across Norway.

Nymo has started the transport of a 1,000-tonne MEG module from Vikkilen to Aker Stord, where it will be integrated into the Valhall PWP project.

The Utility module for Valhall PWP has arrived at Aker Solutions’ Stord yard after sail-away from Stavanger, marking the largest single delivery to the PWP topside and advancing integration ahead of offshore installation.

Sarens has completed the 11,500-tonne load-out of the Valhall PWP jacket at Aker Solutions Verdal, Norway, marking a milestone in offshore heavy-lift engineering.