
RWE Installs 22 Turbines at Nordseecluster A Offshore Wind Farm
RWE has installed 22 of 44 Vestas turbines at the 660 MW Nordseecluster A offshore wind farm, with full grid connection scheduled for the beginning of 2027.

RWE has installed 22 of 44 Vestas turbines at the 660 MW Nordseecluster A offshore wind farm, with full grid connection scheduled for the beginning of 2027.

DeepOcean has completed installation and testing of 48 inter-array cables at Germany’s Nordseecluster A offshore wind farm, using four vessels across the campaign.

DEME’s jack-up vessel Norse Wind has installed the first 15 MW turbine at RWE’s Nordseecluster A project in the German North Sea, where 44 Vestas turbines are planned by the end of 2026.

RWE has installed two offshore substations at Nordseecluster A in the German North Sea, advancing the 660 MW phase of its wider 1.6 GW offshore wind project.

Van Oord’s newest offshore installation vessel Boreas has completed its maiden project, installing 45 monopiles at Nordseecluster A in the German North Sea — a key step in the 1.6 GW Nordseecluster wind farm by RWE and Norges Bank.
For general inquiries and to contact us,
please email: info@hmt-news.com