Harbor Bridge Truss Removed in Corpus Christi

Mammoet removed the 2,300t truss of the US 181 Harbor Bridge in Corpus Christi for TxDOT and FlatironDragados. The structure was lowered 50 meters, loaded onto a barge, and moved using 108 axle lines of SPMT.
Photo source: Mammoet

SHARE ARTICLE

Mammoet completed the removal of the historic US 181 Harbor Bridge in Corpus Christi, Texas, performed as part of the Texas Department of Transportation’s Harbor Bridge Replacement Project for FlatironDragados.
The 2,300t truss was lowered 50 meters using strand jacks, placed on a barge, and transported to a nearby facility with 108 axle lines of SPMT.
With more than 60 years of service, the steel truss bridge reached its final stage of decommissioning as TxDOT advances the new cable-stayed Harbor Bridge.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Sinotrans Sarens completed a 29.600-tonne topside weighing operation for the Yangjiang Sanshandao 500 kV Offshore Wind Project using 230 strand jacks and 230 load cells.
Sarens weighed and loaded out the 24.495-tonne Shell Crux jacket in Batam using hydraulic jacks, strand jacks and SPMTs for the jacket and auxiliary structures.
J M Baxi has completed the transport and marine loadout of 110 L&T CERES Project modules weighing 64,000 tonnes at Kattupalli using 120 Scheuerle Generation 4 SPMT axles.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com