ZHE SHAN Brings Final 7,200 tonnes INEOS Project ONE Module to Antwerp

ZHE SHAN has brought the final 7,200 tonnes module for INEOS Project ONE to Antwerp as construction and commissioning work continues at the ethane cracker site.
Photo credit: Project ONE

SHARE ARTICLE

Heavy transport vessel ZHE SHAN has arrived in Antwerp carrying the second and final major module for INEOS’ Project ONE ethane cracker.

The module weighs 7,200 tonnes and was fabricated in Abu Dhabi. It is one of the final two process modules required to complete the cracker installation at the Project ONE site in Lillo, in the Port of Antwerp.

Transport of the module from Abu Dhabi was disrupted around the Strait of Hormuz. The vessel carrying the cargoes later passed through the strait during a one-week ceasefire in mid-June before continuing to Antwerp via the Suez Canal.

INEOS selected a modular construction method for Project ONE, with process modules and pipe racks assembled at overseas fabrication sites while civil engineering and foundation work progressed in Antwerp. The company said the approach also addressed space constraints at the project site.

Project ONE is a €5 billion engineering project centred on a new ethane cracker in Lillo’s industrial area. The plant is designed for a nameplate production capacity of 1,450 kt of ethylene per year. Ethane will be converted into ethylene at the facility.

With civil engineering work completed and the final module being installed, activity at the Antwerp site has shifted towards mechanical, electrical and instrumentation work. Around 2,500 people from approximately 80 contractors are currently working at the site, with more than 14 million man-hours recorded.

Current work includes the installation of 1,250 km of instrumentation and electrical cables and leak testing. The administrative headquarters, control room and warehouses are also being completed.

The site received permanent electrical power following commissioning of its 380 kV main substation. Commissioning is being carried out in stages as individual subsystems reach mechanical completion.

INEOS has scheduled mechanical completion of the full site for summer 2027 and is targeting start-up of the ethane cracker in the second half of 2027.

Photo credit: Project ONE
Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Hai Long Offshore Wind Project has completed NT$55 billion in additional financing, expanding its group of supporting financial institutions to 35 as construction continues in Taiwan.
ABB will supply four 3.5 MW Azipod units and a power package for Allseas’ 230 m semi-submersible heavy transport vessel Grand Tour, due to enter service in 2028.
Sumitomo Corporation has acquired a 33.3% stake in the up to 1.5 GW Gwynt Glas floating offshore wind project in the UK Celtic Sea, joining EDF power solutions UK and Ireland and ESB.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com