Haizea Wind Group has completed 186 tower sections for 62 Siemens Gamesa offshore wind turbines to be installed at the Dieppe-Le Tréport offshore wind farm in France.
The sections were produced at Haizea Wind Group’s Bilbao factory in Spain. The final shipment has departed the Port of Bilbao for Haizea Breizh in France, where internal components will be completed before offshore installation.
The project is being built 15 km off Le Tréport and 17 km off Dieppe. More than half of the 62 jacket foundations have already been installed. DEME is carrying out the jacket installation, while the foundations were delivered by Navantia Seanergies and Windar Renovables.
The 496 MW wind farm will use 62 Siemens Gamesa 8 MW turbines produced at Le Havre. Turbine installation is scheduled for 2026 by Jan De Nul Group.
The project is owned by Eoliennes en Mer Dieppe Le Tréport, a joint venture between Ocean Winds, Sumitomo and Banque des Territoires.
Dieppe-Le Tréport will be Ocean Winds’ third offshore wind farm in France, after the 488 MW Îles d’Yeu and Noirmoutier project and the 30 MW Éoliennes Flottantes du Golfe du Lion floating wind pilot project.