Zingst OSS Topside Rolls Out in Schiedam

HSI Joint Venture rolled out the 4,700 t OSS Zingst topside in Schiedam, progressing 50Hertz’s 927 MW OST-6-1 grid link for the Gennaker Offshore Wind Farm.
Photo source: Smulders HSM

SHARE ARTICLE

The HSI Joint Venture—comprising HSM Offshore Energy, Smulders, and Iv—has successfully and safely rolled out the topside for OSS Zingst at HSM Offshore Energy’s yard in Schiedam. The milestone advances the delivery of offshore wind transmission infrastructure for 50Hertz.

OSS Zingst is one of two offshore substations, together with OSS Darß, that form the OST-6-1 grid connection in the German Baltic Sea. With a combined transmission capacity of 927 MW, OST-6-1 will connect the Gennaker Offshore Wind Farm to the onshore grid.

The Zingst topside measures 48 m × 33 m × 17.5 m (L × W × H) and weighs 4,700 t. Once installed offshore, the substation will collect and transform 450 MW of power generated by the Gennaker wind farm before transmitting it to shore. The Schiedam roll-out marks a key project step and reflects coordinated progress within the HSI consortium as the work moves toward load-out, sail-away, and offshore installation.

Under the EPCIC contract, the HSI consortium is responsible for the engineering, procurement, construction, installation, and commissioning of the Ostwind3, Zingst, and Darß topsides and their jackets. The joint venture’s integrated execution is intended to support efficient coordination, technical consistency, and established safety and quality standards for a project of this scale.

Located in the German Baltic Sea, OST-6-1 is designed with a transmission capacity of 927 MW. Its two substations—Zingst and Darß—will connect the Gennaker Offshore Wind Farm to 50Hertz’s transmission grid, strengthening regional energy capacity and supporting climate targets in Northern Europe.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The first section of the Lucayan floating drydock departed CSSC Qingdao Beihai Shipbuilding and was loaded onto Boskalis’ Blue Marlin off Qingdao for transport to Grand Bahama Shipyard in the Bahamas.
Seaway7’s semi-submersible heavy transport vessel Seaway Eagle has completed the transport of jack-up rig GMS Enterprise from Dubai to Rotterdam, supporting offshore asset relocation.
HAPO International Barges agreed to buy Hua Dian Bo Qiang 02 (ex Hydrodeck) from Shanghai Bo Qiang Heavy Industries. The 140m x 40m x 12m barge will join as H-461, with handover near Shanghai toward the end of April.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com