Woodfibre LNG Project Surpasses 50% Milestone After Summer Surge in Construction Activity

Woodfibre LNG’s export terminal in Squamish, British Columbia, has passed the halfway point of construction. The company reported visible progress across onshore and offshore works during the summer, including major foundation and module installation milestones.
Image source: Woodfibre LNG

SHARE ARTICLE

Woodfibre LNG’s export terminal in British Columbia has passed the halfway point of construction following a summer marked by visible progress onshore and offshore.

From May through September 2025, crews completed grading, excavation and concrete foundations while managing slope stabilization and erosion controls. Qualified environmental professionals conducted daily site monitoring, including habitat protection measures.

In May, the company received its first seven prefabricated modules, primarily pipe racks linking liquefaction and storage areas. Four additional units arrived in September, including a boil-off gas compressor and flare knock-out drums, both designed to improve operational efficiency and emissions control. In total, 19 modules are scheduled through 2026, ranging from 126 to 11,000 tonnes.

Vertical construction began mid-summer as modules were set in place, marking a visible shift from groundwork toward above-ground assembly. Offshore, piling began for the floating-storage-tank mooring system and LNG carrier berth under permits from the British Columbia Environmental Assessment Office and the Squamish Nation. Marine-mammal observers monitored wildlife, while hydroacoustic monitoring ensured regulatory compliance.

By late September, foundation work, module installation and marine works had advanced the project beyond 50 percent completion, signaling steady momentum as the facility moves into its next phase of construction.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
The heavy load carrier Red Zed 1 delivered the 10,847-tonnes liquefaction module to the Woodfibre LNG project site on 10 March 2026 as the project advances toward completion.
HTV Seaway Swan transports pretreatment and utility modules to the Woodfibre LNG site in Squamish, pushing construction toward 60% completion.
AAL Shipping completed the transport of three LNG plant modules from Hai Phong to British Columbia, demonstrating its expertise in large-scale project cargo and marking its continued operation on the Asia–North America Pacific route.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com