Petrodec Deploys Obana for First North Sea Decommissioning Campaign

Petrodec has deployed its heavy lift jack-up vessel Obana on its first offshore assignment in the Southern North Sea, beginning platform removal work for Perenco UK at the Galahad installation before moving to the Amethyst field.
Petrodec Obana platform (Source: Damen)

SHARE ARTICLE

Petrodec has launched the first commercial offshore campaign for its heavy lift jack-up vessel Obana, deploying the unit in the UK sector of the Southern North Sea for platform removal work contracted by Perenco UK.

The project begins at the Galahad platform in Block 48/12a. After removing the topside and steel jacket at the site, Obana will relocate to the nearby Amethyst field to dismantle three platform jackets identified as C1D, A2D and B1D. Structures recovered during the campaign will be transported to the Netherlands for recycling and disposal.

Built for large-scale offshore decommissioning work, Obana is designed to operate in water depths of up to 65 m. The vessel is equipped with a 2,000 t main crane and provides approximately 3,800 sq m of deck working space.

A key engineering feature is the vessel’s 12,000 t deck load capacity combined with a custom roller system. This arrangement enables large platform modules to be repositioned on deck while offshore, allowing multiple structures to be dismantled and transported during a single campaign without returning to port.

The six-legged vessel was created by combining two retired heavy-duty drilling rigs, Brage and Gabrus, with a newly fabricated midsection built in Dubai. Final integration was completed at Damen Shipyard in Rotterdam. According to the source, around 85% of the vessel’s steel structure is derived from recycled material.

Following the completion of the Perenco UK campaign, Petrodec plans to deploy Obana on additional projects involving the removal of aging offshore infrastructure across the North Sea.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
NMDC Energy expects completion of three offshore EPC projects within 18 to 23 months. The company disclosed their combined value but did not identify the fields or provide individual package prices.
RigCo will fund the work from existing cash. The drillship and jack-up are expected in 2027 and 2028, respectively, while construction plans for the two semi-submersibles remain under assessment.
Borr Drilling confirmed 110 people were safe as air and sea searches continued. BW Energy said no damage or harmful discharge had been reported at MaBoMo, where production was shut down for drilling preparations.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com