First steel cut starts Nederwiek 2 offshore platform build

TenneT marked the first steel cut for Nederwiek 2 on 05 February 2026, the third GE Vernova–Seatrium project in its 2 GW programme, with three platforms now under construction.
Photo source: TenneT

SHARE ARTICLE

On 05 February 2026, TenneT marked the first steel cut for the Nederwiek 2 offshore platform, signalling the formal start of construction. The project is the third under the GE Vernova–Seatrium consortium within TenneT’s 2 GW programme in the Netherlands.

The steel-cutting milestone was observed at two shipyards in Singapore and Indonesia, where the consortium is working with TenneT on Nederwiek 2. Project director Michiel Cadenau described the event as “another important milestone” and said 2026 is expected to be busier than last year, with three platforms of the 2 GW design now under construction. He added that the parties are continuing their collaboration.

TenneT noted that the first 2 GW project, IJmuiden Ver Beta, began construction on 11 September 2024. The second project is IJmuiden Ver Gamma, where the first steel was cut on 14 May 2025.

The 2 GW platforms are intended to collect generated wind energy and transport it to the coast. The green electricity is supplied to millions of customers in the Netherlands and parts of Europe. TenneT is expected to commission the first platform, IJmuiden Ver Beta, in 2029, with more 2 GW platforms, including Nederwiek 2, to follow in the years thereafter.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Pioneering Spirit used its jacket lift system to install both suction bucket foundations and topsides in shallow water for 50Hertz’s OST-6-1 connection, completing the work in one offshore campaign.
Dogger Bank A has secured an eight-month extension to the CfD start date for its first 300 MW contract tranche. The revised July 2027 deadline follows turbine blade failures and additional repair requirements.
Sven Utermöhlen brings 20 years of offshore wind experience to Esvagt. RWE’s succession announcement also provided for him to advise its offshore wind business for six to twelve months after his departure.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com