Equinor Sets 16 January Deadline for Empire Wind Restart

Equinor says Empire Wind 1 could be cancelled unless the US stop-work order is lifted and key construction restarts by 16 January 2026, as the company pursues an injunction.
Image: Eirik Hamre Clausen / Equinor

SHARE ARTICLE

Equinor has warned that its Empire Wind 1 offshore wind project off New York could be cancelled unless a US stop-work order is lifted and critical construction activities can resume by 16 January 2026.

The order was issued on 22 December 2025 by the US Department of the Interior’s Bureau of Ocean Energy Management (BOEM), directing a suspension of ongoing activities on the Outer Continental Shelf and citing national security concerns. Reporting on the federal action has linked the decision to Pentagon concerns about potential radar interference.

In a legal challenge filed in the US District Court for the District of Columbia, Equinor has said the interruption threatens a tightly sequenced construction plan and raises financing risks. The company has indicated that it will seek a preliminary injunction to allow work to continue while the case proceeds.

Equinor has also outlined the scale of its exposure. As of 30 September 2025, the gross book value of Empire Wind 1, including the South Brooklyn Marine Terminal, was about $3.1 billion. As of 30 November 2025, about $2.8 billion had been drawn under the project finance term loan facility. At the time the stop-work order was issued, the company said the project was more than 60% complete.

The halt has triggered further legal action at the state level. New York Attorney General Letitia James has filed lawsuits challenging the federal suspension affecting Empire Wind and Ørsted’s Sunrise Wind project.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
NMDC Energy expects completion of three offshore EPC projects within 18 to 23 months. The company disclosed their combined value but did not identify the fields or provide individual package prices.
RigCo will fund the work from existing cash. The drillship and jack-up are expected in 2027 and 2028, respectively, while construction plans for the two semi-submersibles remain under assessment.
Borr Drilling confirmed 110 people were safe as air and sea searches continued. BW Energy said no damage or harmful discharge had been reported at MaBoMo, where production was shut down for drilling preparations.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com