East Anglia Three to Begin Turbine Installation Using Wind Osprey and Wind Pace

Cadeler will deploy Wind Osprey and Wind Pace to install 95 Siemens Gamesa 14+ MW turbines at East Anglia Three from around 18 March, with completion targeted in 3Q/4Q this year.
Wind Pace (Source: Cadeler)

SHARE ARTICLE

Wind turbine installation at the East Anglia Three offshore wind farm is due to begin around 18 March, with Cadeler deploying its jack-up vessels Wind Osprey and Wind Pace to install 95 Siemens Gamesa 14+ MW turbines. The installation campaign is expected to finish in 3Q or 4Q of this year.

Marine operations for the campaign will be delivered by Cadeler, while construction operations will be handled by turbine supplier Siemens Gamesa, according to a Notice to Mariners issued by the project team.

Both jack-ups will mobilise via the Port of Esbjerg in Denmark. First load-out for Wind Osprey is expected on 15 March, while first load-out for Wind Pace is scheduled for mid-April.

Offshore construction began in April 2025 with installation of the first of 95 monopile foundations at the site, located about 69,000 m off the Suffolk coast. Cadeler’s vessels are being deployed under a Vessel Reservation Agreement signed with ScottishPower Renewables in 2022.

The project is owned by ScottishPower Renewables—the UK arm of Iberdrola—and Masdar, with ScottishPower Renewables leading development, construction and operations on behalf of the partnership.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
PGE has become the sole owner of the 350 MW Baltic II offshore wind project in the Polish Baltic Sea after RWE sold its stake and transferred related environmental rights.
China’s Dajin Heavy Industry is planning an IPO on the Hong Kong Stock Exchange as it looks to access international funding markets and support expansion in fabrication, shipping and renewable energy projects.
Germany’s Bernhard Schulte Offshore has taken delivery of Windea Carnot, the third CSOV in a series built by Ulstein Verft, adding another offshore wind support vessel with hybrid propulsion and capacity for 132 people.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com