Sinotrans Sarens Weighs 29.600-tonne Yangjiang Sanshandao Converter Station

Sinotrans Sarens completed a 29.600-tonne topside weighing operation for the Yangjiang Sanshandao 500 kV Offshore Wind Project using 230 strand jacks and 230 load cells.
Photo source: Sarens

SHARE ARTICLE

Sinotrans Sarens has completed a 29.600-tonne converter station topside weighing operation for ZPMC Nantong as part of the Yangjiang Sanshandao 500 kV Offshore Wind Project.

The one-day operation provided weighing data for the subsequent transport and installation of the topside and for structural safety control. The result exceeded Sarens’ earlier weighing of more than 28.000 tonnes for the Three Gorges Yangjiang Qingzhou Converter Station.

Named “Haifeng Heart”, the converter station has an installed capacity of 2 GW and uses a ±500 kV flexible direct-current transmission system for offshore wind applications. The converter station is described as the world’s largest offshore wind converter station.

Once completed and operational, the project is expected to provide 6 billion kWh of clean energy annually. It is intended to support offshore wind development in China and contribute to the country’s dual-carbon goals.

The topside consists of a seven-floor steel structure covering 7.000 m² and reaching 43 m in height. It is designed for installation on a 75 m high offshore jacket weighing 13.600 tonnes.

The weighing operation was carried out under restricted installation conditions. The equipment had to be installed on 1 m high skidding tracks, with only 680 mm of available installation space. Support piers on both sides of the tracks prevented large machinery from entering the work area.

Sinotrans Sarens distributed the weighing equipment across multiple positions along the skidding tracks. The system comprised 230 strand jacks, 230 load cells, 32 displacement sensors and six pump stations. Equipment weighing up to 450 kg had to be installed manually.

A synchronous closed-loop control system was used to manage load distribution, monitor the weighing process in real time and make adjustments during the operation.

Installation of the complete weighing system took 10 days and was carried out between ongoing construction activities at the site. Joint debugging and calibration required a further half day before the weighing operation was completed.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Boskalis vessel Windpiper has started rock installation at Bałtyk 2 and Bałtyk 3 after loading nearly 45,000 tonnes of rock in Norway for export cable protection.
Heerema Marine Contractors is setting up an engineering hub in Porto, Portugal, to support offshore wind, heavy lift, marine infrastructure and decommissioning projects.
Taiwan plans to begin selecting floating offshore wind demonstration projects in 2027, with two sites expected and a possible third site if necessary.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com