Ørsted Delays Hornsea 3 and Borkum Riffgrund 3 Timelines

Ørsted has revised commissioning timelines for Hornsea 3 and Borkum Riffgrund 3 due to grid operator delays and outages in the UK and Germany.
Orsted CEO Rasmus Errboe. Photo: Orsted

SHARE ARTICLE

Ørsted has revised commissioning schedules for the 2,852 MW Hornsea 3 offshore wind project in the UK and the 913 MW Borkum Riffgrund 3 project in Germany due to grid operator delays and grid outages.

Chief executive Rasmus Errboe said the hold-ups were linked to grid operators in the UK and Germany.

For Hornsea 3, National Grid informed Ørsted that the onshore connection would be delayed by two months. The company has moved the expected commercial operation date from the second half of 2027 to the fourth quarter of 2027 or the first quarter of 2028.

Errboe said Ørsted is taking a cautious approach to the new schedule, but does not expect a meaningful financial impact on the project.

At Borkum Riffgrund 3, turbine commissioning is progressing more slowly than expected, mainly due to curtailment and unplanned outages on the German grid.

Full commissioning has been pushed back by at least four months, from May 2026 to August–September 2026.

Errboe said the revised schedule is not expected to have a meaningful effect on Ørsted’s figures or EBITDA, citing current power prices in Germany.

The German project has commissioned 64 of its 83 turbines.

Errboe said the delays show the need for grid upgrades across Europe as more renewable energy capacity is added.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
NMDC Energy expects completion of three offshore EPC projects within 18 to 23 months. The company disclosed their combined value but did not identify the fields or provide individual package prices.
RigCo will fund the work from existing cash. The drillship and jack-up are expected in 2027 and 2028, respectively, while construction plans for the two semi-submersibles remain under assessment.
Borr Drilling confirmed 110 people were safe as air and sea searches continued. BW Energy said no damage or harmful discharge had been reported at MaBoMo, where production was shut down for drilling preparations.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com