Search
Close this search box

Mammoet Secures Seatrium Substation Load-Out Deal

Mammoet signed an agreement with Seatrium to load out three substations for TenneT’s 2GW HVDC offshore grid programme, using specialist skidding systems for topsides exceeding 30,000 tonnes.
Photo source: TenneT

SHARE ARTICLE

Mammoet has signed an agreement with Seatrium to carry out the load-out of three substations for TenneT’s 2GW offshore grid connection programme.

The work sits within a wider plan to install 15 HVDC grid connection systems in the North Sea by 2032—eight in the Netherlands and seven in Germany—each rated at 2GW.

Under Seatrium’s One Seatrium Global Delivery model, topside fabrication will be carried out across its key yards. Each topside is expected to weigh more than 30,000 tonnes.

Mammoet will manage the movements and load-out using specialist skidding equipment to transfer each structure between land and sea-going transport vessels. The company said its hydraulically compensated skidding systems are intended to support accurate positioning during transfer and reduce structural deflection.

The partners added that deploying higher-capacity systems offshore is expected to support Dutch, German and wider European climate targets while reducing the number of offshore facilities required.

Richard Verhoeff, global sales director at Mammoet, said the company is proud to partner with Seatrium on the programme and will apply engineered solutions to load the structures onto transport vessels in a controlled manner.

Editorial Note:
This article was prepared with the assistance of AI tools to enhance clarity and efficiency.
All information has been reviewed and verified by the HMT News editor.
Boskalis vessel Windpiper has started rock installation at Bałtyk 2 and Bałtyk 3 after loading nearly 45,000 tonnes of rock in Norway for export cable protection.
Heerema Marine Contractors is setting up an engineering hub in Porto, Portugal, to support offshore wind, heavy lift, marine infrastructure and decommissioning projects.
Taiwan plans to begin selecting floating offshore wind demonstration projects in 2027, with two sites expected and a possible third site if necessary.

Subscribe to HMT WEEKLY

Receive HMT WEEKLY in your mailbox.

Heavy Marine Transport News, Delivered Daily — Stay informed on shipping, offshore, and global logistics.

SECTION

INFORMATION

CONTACT

For general inquiries and to contact us,
please email: info@hmt-news.com